The muscle we forgot: SMRs, hyperscalers, and why this nuclear renaissance might actually be different

The muscle we forgot: SMRs, hyperscalers, and why this nuclear renaissance might actually be different

Why nuclear has never been project financed and how that might finally be about to change.

Every nuclear plant ever built has ultimately been backstopped by taxpayers or ratepayers. Not because the technology doesn't work, but because nobody has ever cracked the construction cost and schedule problem well enough to convince a bank to finance it without government support. Bridget van Dorsten is joined by Jake Jurewicz, Co-founder and CEO of Blue Energy, to explore why that has been so hard and what a credible path to fixing it might actually look like.

Jake walks through the root cause of nuclear's cost overrun problem and it is not the reactor. The reactor equipment itself represents around 7% of total project costs. The real problem is what Jake calls nuclear construction overhead: the cost of mobilizing, training, and retaining the 10,000 or so skilled workers needed to build these plants in the field, the way we have been building them for 70 years, essentially the same way you would build a castle.

The episode then turns to what Blue Energy is doing differently. By intentionally selecting sites accessible by barge and contracting existing oil and gas fabrication yards and shipyards to build large pre-assembled modules offsite, Blue Energy aims to bring fixed-price contracts into nuclear for the first time, the same contracting structure that made offshore wind and LNG bankable. Jake explains why that single shift changes everything for project financing.

Bridget and Jake also work through the demand side of the equation: why hyperscalers are becoming the crucial beachhead market for new nuclear, what binding PPAs from investment-grade counterparties actually signal versus announcements, and why the restarts and uprates, while valuable, only go so far.

The conversation also covers Blue Energy's first announced project at the Port of Victoria in Texas, a 1.5 gigawatt nuclear-powered AI data centre co-located with a gas-to-nuclear conversion, designed to accelerate commercial operation and reduce cost of capital even without government loan support. Jake explains the mechanics of why firing the balance of plant with gas first before switching to nuclear steam is not a compromise but a genuine financing innovation.

Finally, Jake offers a view of what signals actually matter when separating the nuclear renaissance from the noise: binding PPAs, large balance sheets standing behind fixed-price contracts, and projects moving through the Nuclear Regulatory Commission rather than staying at the prototype stage.

See Privacy Policy at https://art19.com/privacy and California Privacy Notice at https://art19.com/privacy#do-not-sell-my-info.

Jaksot(342)

Speed or Sustainability - Will We Always Have to Choose?

Speed or Sustainability - Will We Always Have to Choose?

With major airline companies setting net zero goals by 2050, we’ve talked a lot about the aviation industry and its contribution to our emissions problem. In recent episodes we have featured several...

16 Syys 202241min

Solving the Food-Cooling Conundrum: Making Storage Sustainable

Solving the Food-Cooling Conundrum: Making Storage Sustainable

It’s something we reiterate every episode: we’ll achieve net zero by adopting the new energy transition technologies that are developed every day around the world. Often we focus on the main areas: th...

2 Syys 202244min

Could Hydrogen Power the Future of Flight?

Could Hydrogen Power the Future of Flight?

Today, the global aviation industry is responsible for around two percent of carbon dioxide emissions. With major airlines pledging to hit net-zero by 2050, all eyes are on sustainable fuel manufactur...

19 Elo 202245min

A New Way of Procuring Energy

A New Way of Procuring Energy

We talk a lot on the podcast about the technology that powers the latest innovations in energy supply. But what about a solution to the problem of energy procurement?A few episodes ago, we spoke to th...

5 Elo 202233min

How Wave Power Can Supplement Wind & Solar

How Wave Power Can Supplement Wind & Solar

The energy transition is a machine with hundreds of moving parts. The problems we face in getting to net zero will be solved by a combination of technology, policy and consumer action. The cleantech s...

22 Heinä 202238min

The Ever-Changing Role of PPAs In The Energy Transition

The Ever-Changing Role of PPAs In The Energy Transition

9 months ago The Interchange spoke with Harald Overholm from Alight. Alight is one of the leading providers of Power Purchase Agreements in Europe. Since then we’ve seen massive changes in the market,...

8 Heinä 202241min

Green Tech Investments, Green Washing and SPACS

Green Tech Investments, Green Washing and SPACS

To continue to accelerate the energy transition investment in clean tech companies is essential. We’ve seen more growth in the last 5 years than the last 100 with trillions of dollars flooding the mar...

24 Kesä 202248min

The Interchange: Live At The Solar & Energy Storage Summit - Day 3 Recap

The Interchange: Live At The Solar & Energy Storage Summit - Day 3 Recap

Wood Mackenzie’s Solar Energy and Storage Summit has wrapped for 2022.Across 3 days of talks on solar and storage, we were live in San Diego, bringing you highlights from each day of the conference.On...

10 Kesä 20221h 5min

Suosittua kategoriassa Liike-elämä ja talous

sijotuskasti
mimmit-sijoittaa
psykopodiaa-podcast
rss-rahapodi
rss-sisalto-kuntoon
rss-rahamania
ostan-asuntoja-podcast
rahapuhetta
herrasmieshakkerit
sijoituspodi
rss-karon-grilli
leadcast
asuntoasiaa-paivakirjat
rss-lahtijat
rss-startup-ministerio
rss-paasipodi
rss-yrittajan-mindset
rss-draivi
pomojen-suusta
rss-valaistumisia-tyoelamasta